- Client:
Randgold Resources - Classification:
SMPPE Brownfields - Key Project Data:
Quaternary Crushing Systems - Mineral:
Gold & Silver - Date:
2015 - 2016
Tongon Crushing, Fabrication and Installation Project
SMPPE Brownfields Quaternary Crushing, Tongon Gold Plant in Côte d'Ivoire
Randgold Resources completed the Quaternary Crushing Project. The project included a fourth stage crushing system to reduce the mill feed size to improve plant throughput when mining harder sulphide ores.
Services
AZMET was appointed for the supply & installation of all steelwork, mechanical equipment, platework, piping & electrical equipment of the Quaternary Crushing System. The scope of work included the following equipment:
-
350t Structural Steel & Plate Work
Cone Crushers
New Conveyor Belting & Chutes
Extend existing conveyor to feed new crushing circuit
300t Feed Bin
Fines Removal Screens
Slurry Pumps
Piping & Valves
Cabling & Racking
MCC & PLC