Tongon Crushing, Fabrication and Installation Project

Randgold Resources

  • Client:
    Randgold Resources
  • Classification:
    SMPPE Brownfields
  • Key Project Data:
    Quaternary Crushing Systems
  • Mineral:
    Gold & Silver
  • Date:
    2015 - 2016

Tongon Crushing, Fabrication and Installation Project

SMPPE Brownfields Quaternary Crushing, Tongon Gold Plant in Côte d'Ivoire

Randgold Resources completed the Quaternary Crushing Project. The project included a fourth stage crushing system to reduce the mill feed size to improve plant throughput when mining harder sulphide ores.

Services


AZMET was appointed for the supply & installation of all steelwork, mechanical equipment, platework, piping & electrical equipment of the Quaternary Crushing System. The scope of work included the following equipment:

    350t Structural Steel & Plate Work
    Cone Crushers
    New Conveyor Belting & Chutes
    Extend existing conveyor to feed new crushing circuit
    300t Feed Bin
    Fines Removal Screens
    Slurry Pumps
    Piping & Valves
    Cabling & Racking
    MCC & PLC