In Q1,2017 AZMET has been awarded an EPCM contract for the design, supply and commissioning of a 4 ton Carbon Batch, Gold Adsorption, Desorption and Recovery Plant (ADR Plant) for the Lydian Amulsar gold heap leach operation in Armenia.


Read more

Armenia
Armenia

In Q4,2015 AZMET has been awarded a LSTK contract for the design, supply and commissioning of a containerised, 2 ton Carbon Batch, Gold Desorption and Recovery Plant (DR Plant) for the Meli Gold Mine in Ethiopia.


Read more

Ethiopia
Ethiopia

In Q1,2016 AZMET has been awarded a LSTK contract for the design, supply and commissioning of a containerised, 2 ton Carbon Batch, Gold Desorption and Recovery Plant (DR Plant) for the Eti Bakir operations In Turkey.


Read more

Turkey
Turkey
Eti Bakir – Gold 2t DR Plant & Reagent Systems

In Q1,2016 AZMET has been awarded a LSTK contract for the design, supply and commissioning of a containerised, 2 ton Carbon Batch, Gold Desorption and Recovery Plant (DR Plant) for the Eti Bakir operations In Turkey, incorporating the following processes:

  • Carbon Handling,
  • Acid wash,
  • Elution (Pressure Zadra)
  • Electrowinning with Ammonia & Mercury Scrubber Systems
  • Goldroom (brick building) & Security with Mercury Retort & Mercury Scrubber System
  • Carbon Regeneration with a Mercury Scrubber System
  • All related Reagent Make-up & Dosing Systems,
  • MCC & PLC.

In addition to the AZMET DR Plant, modular reagent make-up and dosing systems formed part of the supply contract, incorporating Cyanide, Caustic, Lime, Hydrochloric Acid and Detox (CuSO4 & SMBS).

Containerised Modules were ordered for supply and will be completed in 2018.

 

 

All