In Q1,2017 AZMET has been awarded an EPCM contract for the design, supply and commissioning of a 4 ton Carbon Batch, Gold Adsorption, Desorption and Recovery Plant (ADR Plant) for the Lydian Amulsar gold heap leach operation in Armenia.


Read more

Armenia
Armenia

In Q4,2015 AZMET has been awarded a LSTK contract for the design, supply and commissioning of a containerised, 2 ton Carbon Batch, Gold Desorption and Recovery Plant (DR Plant) for the Meli Gold Mine in Ethiopia.


Read more

Ethiopia
Ethiopia

In Q1,2016 AZMET has been awarded a LSTK contract for the design, supply and commissioning of a containerised, 2 ton Carbon Batch, Gold Desorption and Recovery Plant (DR Plant) for the Eti Bakir operations In Turkey.


Read more

Turkey
Turkey
AZMET’s Modular/Containerised Gold Desorption & Recovery Plant (AZ-DRP)

AZMET’s Modular/Containerised Desorption and Recovery Plant for Gold & Silver hold numerous advantages for the end user and EPCM contractor. The total modular plant is assembled and cold commissioned (as practically possible) prior to shipment to minimise the project time schedule for site installation and hot commissioning, with minimal changes.

Design of supply is flexible and can be adjusted per the client’s needs; with a total supply consisting of six (6) independent modules.

AZMET has seen a drastic increase in our clients’ needs for modular/containerised plants across the globe. This again is confirmation of the benefits and project savings that

can be recognised when procuring AZMET’s proprietary products.